CDT’s first water surface floating photovoltaic power plant connected to grid for power generation

2020-06-16

On December 29, 2019, Datang?Huayin?Ruanjiang?Renewable Energy Co., Ltd. brought good news: Beigang?Changhe?100 MW photovoltaic project, CDT’s first water surface floating photovoltaic power plant, was successfully connected to the grid for power generation. It is the first large-scale water surface floating photovoltaic power project in CDT and Hunan Province.

Since the project started on October 13, CDT Hunan Branch Company has been working on fast track and completed this project and achieved grid connection within just 78 days.

The project adopts the high-power single-crystal silicon photovoltaic module technology, a technology with the highest conversion rate per unit area in the world at the moment, and a high-power centralized inverter, with photoelectric conversion rate reaching 19.8%; at the same time, the unique water surface floating technology and anchor system is adopted, which can increase power generation by about 5%. According to estimates, the project is expected to have an average annual grid-connected power of 125 GWh. The "sunshine wealth" has brought five harvests of "fishing, electricity, tourism, environmental protection, taxation", making contributions to local economy and ecological conservation.


Copyright? www.lynsmy.com All Rights Reserved

Address: 1 Guaningbo St., Xicheng Dist., Beijing 100033

Email: cdt-info@china-cdt.com

CDT WeChat

CDT Micro-blog

Produced By CMS 網(wǎng)站群內(nèi)容管理系統(tǒng) publishdate:2025-03-05 12:00:35
兴山县| 陕西省| 新营市| 新乐市| 修水县| 敦煌市| 晋中市| 辽宁省| 河西区| 凤翔县| 托里县| 基隆市| 板桥市| 永康市| 收藏| 灵石县| 南溪县| 繁峙县| 南陵县| 龙里县| 定州市| 桃江县| 南丰县| 汽车| 阳江市| 玉田县| 台安县| 化州市| 错那县| 甘南县| 汶上县| 桃园县| 巫溪县| 特克斯县| 昌平区| 江西省| 体育| 芜湖市| 平南县| 马龙县| 宁河县|